|
|
Bayfield Street Beautification Survey Results
The Bayfield Street Beautification Committee will be hosting two meeting to go over the results of the survey that that was done, and to take in additional comments. Please join in. These will occur at the The Club.
Update - Phase 1
Bayfield Street Reconstruction Project October 17, 2023 In preparation for the Bayfield Street Phase 1 Project occurring next year; the grading and paving of Holman Lakeview Dr. and the milling and paving of Bigelow St. is scheduled to start on October 28th, weather permitting. This work is being done as part of the detour route for the project. There will be about a week of work that will start with adding gravel base on Holman Lakeview Dr., the milling of Bigelow, and then the paving of both streets. The streets will not get pavement markings until the spring. Residents along the route will still be able to access their homes, but the roads will be closed to all other traffic. In addition, the City is changing the stop sign configuration of all the intersecting streets along this route. There will be four-way stops at all intersections until after the paving is completed at which point the stop signs along Holman Lakeview and Bigelow will be removed. Because of this work, the City will be removing the docks at the Thompson’s West End Boat Ramp prior to October 28th. Public Meeting - Phase 2 Bayfield Street Reconstruction Project July 17, 2023
The Wisconsin Department of Transportation (WisDOT) held a Public Involvement Meeting regarding the proposed reconstruction project on WIS 13 from the Washington Ave. to Superior Ave. in the City of Washburn. The proposed improvements would consist of removing and reconstructing the existing pavement with concrete pavement, replacing the curb and gutter and sidewalk. Other proposed work will consist of replacing storm sewer, sanitary sewer, watermain and streetlights. Below is a recording of the meeting, with presentation (about 60 min.) and the Q&A period following. You can also find the comment form below, or contact the project manager for any specific questions of the WisDOT's scope of work: Jessica Bowker, WisDOT Project Manager 718 West Clairemont Ave., Eau Claire, WI 54701, by email at Jessica.Bowker@dot.wi.gov, or by telephone at (715) 577-2963.
|
Scope of Work
Project Goals
Phase 1 - (2nd Ave W to Thompson Creek)
Phase 2 - (2nd Ave W to Superior Ave)
We would like your feedback as we continue working with WisDOT. Please click the button below to leave your comments.
|
This is the background of the Bottom Area shown below. It'll display correctly on published site.
If you don't want background for the bottom area, simply hover over the bottom of this image to delete it. The background of the bottom area will be a solid dark color.
|
©2020 CITY OF WASHBURN. ALL RIGHTS RESERVED.
WEBSITE BY BIZY DOES IT
The City of Washburn complies with federal and state disability laws and makes reasonable accommodations for customers and citizens with disabilities. If reasonable accommodation is
needed for any service, please contact: Scott Kluver, Administrator/ADA Coordinator, 715-373-6160, Ext. 4 or by email: administrator -at- cityofwashburnwi -dot- gov |